The Auro Sapphire payment plan makes buying a premium apartment easy and stress-free. Buyers pay in stages based on how the construction moves forward. The plan starts with 10% at booking. Next, buyers pay 10% within 30 days of booking. After that, 10% is paid when the footings begin. The remaining amount is paid in 5% parts at the podium, slab, finishing and handover stages until possession. This payment plan clearly shows how much to pay and when to pay at every stage. It is easy to understand and helps buyers plan their money smoothly without any stress.

Step-by-Step Payment Schedule of Auro Sapphire

The Auro Sapphire payment plan follows a construction-linked instalment model where payments are spread across major construction stages as the building takes shape. Here's how the schedule works:

As per the official launch price sheet (24 October 2026), the instalments are linked to these milestones:

  • Booking Amount: 10% of the sale consideration
  • Within 30 days from the date of booking: 10%
  • On commencement of footings: 10%
  • On commencement of podium: 5%
  • On commencement of the 5th floor slab: 5%
  • On commencement of the 10th floor slab: 5%
  • On commencement of the 15th floor slab: 5%
  • On commencement of the 20th floor slab: 5%
  • On commencement of the 25th floor slab: 5%
  • On commencement of the 30th floor slab: 5%
  • On commencement of the 35th floor slab: 5%
  • On commencement of the 40th floor slab: 5%
  • On commencement of the 45th floor slab: 5%
  • On commencement of the terrace slab: 5%
  • On commencement of external painting: 5%
  • On commencement of flooring: 5%
  • On commencement of registration & handover: 5%

Booking & within 30 days (20%): 10% of the sale consideration is paid at booking and another 10% within 30 days, which secures your chosen unit.

Footings & podium (15%): 10% falls due when the footings begin and 5% when the podium begins, linking payments directly to on-site progress.

Slab stages (45%): 5% is due at the start of every fifth floor slab, from the 5th to the 45th floor, across all 47-floor towers.

Finishing & handover (20%): 5% each on the terrace slab, external painting, flooring, and finally registration & handover, scheduled with possession on 30 November 2031.

Additional Charges & Buyer Costs


Apart from the instalment payments linked to construction progress, buyers should also plan for a few additional costs that are not included in the base apartment price. As per the launch price sheet, these are the charges that apply:

  • Launch Base Price: ₹9,199 per sq ft
  • Floor Rise: ₹25 per sq ft per floor (from the 5th floor)
  • Facing Premium: ₹150 per sq ft (east-facing units)
  • Corner Premium: ₹200 per sq ft
  • Car Parking (each): Basement I (1st–4th & 41st–47th floors) ₹4,75,000; Basement II (29th–40th floors) ₹4,00,000; Basement III (17th–28th floors) ₹3,50,000; Basement IV (5th–16th floors) ₹3,00,000
  • Infrastructure Development Charges (water, electricity, DG, STP, gas pipeline, solar, WTP etc.): ₹350 per sq ft
  • Club House & Amenities: ₹3,50,000
  • Advance Maintenance for 2 years: ₹108 per sq ft + GST
  • Corpus Fund: ₹50 per sq ft
  • Legal & Documentation Charges: ₹35,000 + GST
  • Deposits: Non-refundable deposit ₹50,000 and refundable caution deposit ₹25,000
  • Taxes: GST at 5% on the sale consideration and 18% on other charges

Also payable: registration and stamp duty as per Telangana state regulations.

Cancellation and Payment Terms

  • ₹50,000 is deducted for cancellation before the Agreement of Sale (AOS); 10% of the sale consideration is deducted after the AOS.
  • Payments are accepted only from the applicant and co-applicants; third-party payments are not accepted.
  • All payments must be made strictly as per the milestone schedule; delays attract interest and may lead to cancellation of the unit.
  • Prices are subject to change without prior notice.

Why This Payment Plan Helps Buyers


The Auro Sapphire payment plan makes home buying easy. Buyers do not have to pay a large amount all at once. Instead, payments are spread out over different stages of construction. Each payment is linked to construction progress, so it is easy to understand when a payment is due. This clear plan helps buyers manage their money better, avoids confusion, and builds confidence by matching payments with real work done at the site.

Enquiry
Enquire Now